[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100945":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100945,779,1,"单选题","在设计施工总承包合同中，关于竣工试验，通用条款规定的竣工试验程序按三阶段进行，其中第二阶段是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人进行试验，保证每一项工程设备满足合同要求",false,{"key":16,"text":17,"correct":14},"B","发包人进行试验，保证工程或区段工程满足合同要求",{"key":19,"text":20,"correct":14},"C","承包人进行试验，保证每一项工程设备满足合同要求",{"key":22,"text":23,"correct":24},"D","承包人进行试验，保证工程或区段工程满足合同要求",true,"2020版教材P136-137 第三阶段，承包人进行试验，保证工程或区段工程满足合同要求，在所有可利用的操作条件下安全运行;",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]