[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100944":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100944,779,1,"单选题","设计施工总承包合同模式下，承包人应提前()天将申请竣工试验的通知送达监理人，并按照专用条款约定的份数向监理人提交竣工记录、暂行操作和维修手册。监理人应在()天内，确定竣工试验的具体时间。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","14，21",false,{"key":16,"text":17,"correct":14},"B","14，14",{"key":19,"text":20,"correct":14},"C","21，21",{"key":22,"text":23,"correct":24},"D","21，14",true,"2020版教材P136-137 本题考查的是竣工验收管理。承包人应提前21天将申请竣工试验的通知送达监理人，并按照专用条款约定的份数，向监理人提交竣工记录、暂行操作和维修手册。监理人应在14天内，确定竣工试验的具体时间 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]