[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100941":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100941,779,1,"单选题","在对以往历次已签发的进度付款证书进行汇总和复核中发现错、漏或重复情况时，监理人有权予以修正，承包人也有权提出修正申请。经监理人、承包人复核同意的修正，应在( )支付或扣除。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","竣工结算",false,{"key":16,"text":17,"correct":14},"B","下一次进度款中",{"key":19,"text":20,"correct":21},"C","本次进度付款中",true,{"key":23,"text":24,"correct":14},"D","以上都不正确","2020版教材P129-131 本题考查的是工程款支付管理。在对以往历次已签发的进度付款证书进行汇总和复核中发现错、漏或重复情况时，监理人有权予以修正，承包人也有权提出修正申请。经监理人、承包人复核同意的修正，应在本次进度付款中支付或扣除 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]