[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100937":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100937,779,1,"单选题","设计施工总承包合同模式下，承包人的设计文件提交监理人后，为了不影响后续工作，自监理人收到承包人的设计文件之日起，对承包人的设计文件审查期限不超过( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","28",false,{"key":16,"text":17,"correct":18},"B","21",true,{"key":20,"text":21,"correct":14},"C","14",{"key":23,"text":24,"correct":14},"D","7","2020版教材P127-128 本题考查的是设计工作的合同管理。为了不影响后续工作，自监理人收到承包人的设计文件之日起，对承包人的设计文件审查期限不超过21天。承包人的设计与合同约定有偏离时，应在提交设计文件的通知中予以说明。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]