[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100936":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100936,779,1,"单选题","根据《标准设计施工总承包合同》，需政府有关部门审查或批准的设计文件，发包人应在对其审查同意后的( )日内向政府有关部门报送审查。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","15",false,{"key":20,"text":21,"correct":18},"C","21",{"key":23,"text":24,"correct":18},"D","30","2020版教材P127-128 本题考查的是设计工作的合同管理。设计文件需政府有关部门审查或批准的工程，发包人应在审查同意承包人的设计文件后7天内，向政府有关部门报送设计文件，承包人予以协助。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]