[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100925":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100925,779,1,"单选题","根据《标准设计施工总承包招标文件》中的《合同条款及格式》，“发包人要求”中竣工试验的第三阶段应对（ ）提出要求。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","联动试车",false,{"key":16,"text":17,"correct":18},"B","性能测试",true,{"key":20,"text":21,"correct":14},"C","单车试验",{"key":23,"text":24,"correct":14},"D","投料试车","2020版教材P121-123 竣工试验：(1)第一阶段，如对单车试验等的要求，包括试验前准备；(2)第二阶段，如对联动试车、投料试车等的要求，包括人员、设备、材料、燃料、电力、消耗品、工具等必要条件；(3)第三阶段，如对性能测试及其他竣工试验的要求，包括产能指标、产品质量标准、运营指标、环保指标等。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]