[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100905":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100905,779,1,"单选题","设计施工总承包合同模式下，关于价格清单的说法错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","与施工招标由发包人依据设计图纸的概算量提出工程量清单，经承包人填写单价后计算价格的方式不同",false,{"key":16,"text":17,"correct":14},"B","承包人按投标文件中规定的格式和要求填写，并标明价格的报价单",{"key":19,"text":20,"correct":14},"C","清单价格费用的总和为签约合同价",{"key":22,"text":23,"correct":24},"D","承包人完成所提投标方案计算的施工、竣工阶段的计划费用",true,"2020版教材P121-123 本题考查的是合同文件。选项D，价格清单是指承包人完成所提投标方案计算的设计、施工、竣工、试运行、缺陷责任期各阶段的计划费用，清单价格费用的总和为签约合同价 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]