[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100900":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100900,779,1,"单选题","根据《设计施工总承包合同》，关于建设工程监理人的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人同意分包的工作，承包人应向发包人和监理人提交分包合同副本",false,{"key":16,"text":17,"correct":18},"B","发包人分包工作需要征得监理人同意",true,{"key":20,"text":21,"correct":14},"C","承包人对总监理工程师授权的监理人员发出的指示有疑问时，可在该指示发出的48小时内向总监理工程师提出书面异议",{"key":23,"text":24,"correct":14},"D","监理人应审查分包人的资格能力","发包人分包工作，不需要监理工程师同意。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]