[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100891":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100891,779,1,"单选题","根据《标准设计施工总承包合同》，关于工程分包的说法，正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人不得将其承包的工程分包给第三人",false,{"key":16,"text":17,"correct":14},"B","投标文件中已说明的分包，合同履行还需再征得发包人同意",{"key":19,"text":20,"correct":21},"C","承包人不得将设计和施工的主体、关键性工作的施工分包给第三人",true,{"key":23,"text":24,"correct":14},"D","委托分包人的工作由发包人和承包人共同完成","2020版教材P120-121 承包人不得将设计和施工的主体、关键性工作的施工分包给第三人。要求承包人是具有实施工程设计和施工能力的合格主体，而非皮包公司。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]