[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100890":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100890,779,1,"单选题","下列关于设计施工总承包合同模式下分包工程的说法，错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人不得将其承包的全部工程肢解后以分包的名义分别转包给第三人",false,{"key":16,"text":17,"correct":18},"B","分包人的资质能力不需要经过监理人审查",true,{"key":20,"text":21,"correct":14},"C","承包人不得将设计和施工的主体、关键性工作的施工分包给第三人",{"key":23,"text":24,"correct":14},"D","除发包人已同意投标文件中说明的分包外，合同履行过程中承包人还需分包的工作仍需要经发包人同意","2020版教材P120-121 本题考查的是设计施工总承包合同管理有关各方的职责。选项B，分包人的资格能力应与其分包工作的标准和规模相适应，其资质能力的材料应经监理人审查 。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]