[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100886":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100886,779,1,"单选题","设计施工总承包中，由于在招标文件中发包人仅对项目的建设提出具体要求，实际方案由（ ）提出，设计可能受到实施者利益影响，对工程实施成本的考虑往往会影响到设计方案的优化。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理人",false,{"key":16,"text":17,"correct":14},"B","技术负责人",{"key":19,"text":20,"correct":21},"C","承包人",true,{"key":23,"text":24,"correct":14},"D","勘察人","2020版教材P120 设计施工总承包中，由于在招标文件中发包人仅对项目的建设提出具体要求，实际方案由承包人提出，设计可能受到实施者利益影响，对工程实施成本的考虑往往会影响到设计方案的优化。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]