[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100857":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100857,779,1,"单选题","决定建设项目性能，优化和控制工程质量及工程造价最关键、最有利的阶段是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计阶段",true,{"key":16,"text":17,"correct":18},"B","施工阶段",false,{"key":20,"text":21,"correct":18},"C","决策阶段",{"key":23,"text":24,"correct":18},"D","实施阶段","2020版教材P25-26 在招标标的物特征上，勘察设计是工程建设项目前期最为重要的工作内容，设计阶段是决定建设项目性能，优化和控制工程质量及工程造价最关键、最有利的阶段，设计成果将对工程建设和项目交付使用后的综合效益起重要作用。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]