[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100816":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100816,779,1,"单选题","关于建设工程勘察设计合同的发包说法，错误的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设工程勘察设计单位不可以将其业务转包",false,{"key":16,"text":17,"correct":14},"B","可以将整个建设工程的勘察设计发包给一个单位",{"key":19,"text":20,"correct":21},"C","建设工程主体部分的设计可以分包",true,{"key":23,"text":24,"correct":14},"D","可以将整个建设工程的勘察设计发包给多个单位","2020版教材P30-34 除投标文件中规定的非主体、非关键性设计工作外，其他工作不得分包。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]