[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100786,779,1,"单选题","投标人或者利害关系人对招标文件有异议时，下列做法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应当在投标截止时间10日前提出",true,{"key":16,"text":17,"correct":18},"B","可以以口头形式提出",false,{"key":20,"text":21,"correct":18},"C","招标人应当在收到异议之日起5日内作出答复",{"key":23,"text":24,"correct":18},"D","招标人作出答复前，可以不暂停招标投标活动","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]