[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100785":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100785,779,1,"单选题","下列设计承包人对其承包的设计工作进行分包的行为正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分包主体.关键性设计工作",false,{"key":16,"text":17,"correct":14},"B","经发包人同意后，分包主体.关键性设计工作",{"key":19,"text":20,"correct":14},"C","分包非主体.非关键性设计工作",{"key":22,"text":23,"correct":24},"D","经发包人同意后，分包非主体.非关键性设计工作",true,"2、分包 （1）禁止分包主体、关键性工作（不论发包方是否同意）； （2）禁止未经发包方书面同意分包非主体、非关键性的工作（发包方同意后才可分包）。 （3）中标人应当就分包项目向招标人负责； （4）分包人就分包项目与中标人向招标人承担连带责任。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]