[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100764":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100764,779,1,"单选题","（2020年真题）关于投标限价的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标文件中可设置最低投标限价的具体金额",false,{"key":16,"text":17,"correct":14},"B","招标文件中应规定投标价低于最高投标限价的幅度",{"key":19,"text":20,"correct":14},"C","投标人的投标价超出最高投标限价时，应增加其评标价格",{"key":22,"text":23,"correct":24},"D","招标人可在招标文件中仅规定最高投标限价的计算方法",true,"P72-74 招标文件是否设置最高投标限价。如设置，招标文件中应明确最高投标限价金额或最高投标限价的计算方法。若投标人的投标价格超出最高投标限价，其投标将被否决。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]