[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100743":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100743,779,1,"单选题","采用招标方式采购运行期内各种费用较高的通用成套设备，评标时的正确做法是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不宜将交货期作为评标内容",false,{"key":16,"text":17,"correct":14},"B","宜将报价最低者作为中标人",{"key":19,"text":20,"correct":21},"C","宜采用设备寿命周期成本为基础的评标价法",true,{"key":23,"text":24,"correct":14},"D","宜采用综合评估法","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]