[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100742,779,1,"单选题","采用招标方式采购运行期内各种费用较高的通用成套设备，下列对运营费用这一评审要素进行折价并对投标报价作价格调整不正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","应当计算的费用包括评审寿命期内所需的燃料消耗费.备件及维修费用以及寿命期末设备残值",false,{"key":16,"text":17,"correct":14},"B","评审寿命期内所需的燃料消耗费.备件及维修费用，按预定的方法折算后，增加投标价",{"key":19,"text":20,"correct":21},"C","评审寿命期末设备残值，按预定的方法折算后，增加投标价",true,{"key":23,"text":24,"correct":14},"D","计算各项费用和残值时，均应按招标文件规定的贴现率折算成净现值","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]