[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100728":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100728,779,1,"单选题","某国外设备投标的到岸价为300万美元，评审供货范围偏差增加评标价4万美元，商务偏差调整值为+2．5％，技术偏差调整值为+3％，则该设备投标价格的调整额为( )万美元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7．5",false,{"key":16,"text":17,"correct":14},"B","11．5",{"key":19,"text":20,"correct":14},"C","13．0",{"key":22,"text":23,"correct":24},"D","20．5",true,"2020版教材P68-70 价格调整额=供货范围偏差调整额+商务偏差调整额+技术偏差调整额=4+300×2．5％+300×3％=20．5万美元。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]