[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100704,779,1,"单选题","材料设备采购批次标包划分说法错误的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","要避免划分过大，缺乏对大型供应厂商的吸引力",true,{"key":16,"text":17,"correct":18},"B","标包的划分要考虑工程实际需要，保证货物质量和供货时间",false,{"key":20,"text":21,"correct":18},"C","每次招标时，可依据设备材料的性质只发一个标包或分成几个标包同时招标",{"key":23,"text":24,"correct":18},"D","投标人可以投一个或其中的几个标包，但不能仅对-个标包中的某几项进行投标。","2020版教材P62-63 标包的划分要考虑工程实际需要，保证货物质量和供货时间，并有利于吸引多家投标人参加竞争，既要避免标包划分过大，中小供应厂商无法满足供应;又要避免划分过小，缺乏对大型供应厂商的吸引力。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]