[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100675":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100675,779,1,"单选题","(2017年真题)建设工程项目的招标人发现招标文件有错误时，应在投标截止时间15日前通知投标人，同时进 行的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以书面形式修改招标文件，但不延长投标截止日期",true,{"key":16,"text":17,"correct":18},"B","以口头形式修改招标文件，但不延长投标截止日期",false,{"key":20,"text":21,"correct":18},"C","以书面形式修改招标文件，并延长投标截止日期",{"key":23,"text":24,"correct":18},"D","以口头形式修改招标文件，并延长投标截止日期","投标预备会的会议纪要、对投标人质疑的书面解答和招标文件的修改均构成招标文件的组成部分，如果与发售 的招标文件出现矛盾或歧义，以时间靠后的文件为准。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]