[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100652":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100652,779,1,"单选题","关于评标，下列说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","评标过程中，招标委员会书面要求投标人对其投标文件中不明确的内容说明",false,{"key":16,"text":17,"correct":18},"B","评标委员会接受投标人主动提出的澄清",true,{"key":20,"text":21,"correct":14},"C","综合评估法要采用初步评审和详细评审两阶段",{"key":23,"text":24,"correct":14},"D","最低投标价法要采用初步评审和详细评审两阶段","2020版教材P54-57 评标委员会不接受投标人主动提出的澄清、说明或补正。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]