[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100647":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100647,779,1,"单选题","根据《标准施工招标文件》，下列评审工作中，不属于详细评审阶段工作内容的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工组织设计",false,{"key":16,"text":17,"correct":14},"B","项目管理机构",{"key":19,"text":20,"correct":21},"C","响应性评审",true,{"key":23,"text":24,"correct":14},"D","投标报价","2020版教材P54-57 综合评估法与最低评标价法初步评审标准的参考因素与评审标准等方面基本相同，只是综合评估法初步评审标准包含形式评审标准、资格评审标准和响应性评审标准三部分。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]