[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100632":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100632,779,1,"单选题","招标人应当合理确定提交资格预审申请文件的时间，自资格预审文件停止发售之日起不得少于()日。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",true,{"key":16,"text":17,"correct":18},"B","10",false,{"key":20,"text":21,"correct":18},"C","15",{"key":23,"text":24,"correct":18},"D","30","2020版教材P40-49 招标人应当按照资格预审公告规定的时间、地点发售资格预审文件。给潜在投标人准备资格预审文件的时间应不少于5日",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]