[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100626":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100626,779,1,"单选题","质量管理体系和环境保护管理体系的完整性、措施的有效性属于( )的内容。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","形式评审",false,{"key":16,"text":17,"correct":14},"B","资格评审",{"key":19,"text":20,"correct":14},"C","响应性评审",{"key":22,"text":23,"correct":24},"D","施工组织设计和项目管理机构评审",true,"2020版教材P54-57 施工组织设计和项目管理机构评审的因素一般包括施工方案与技术措施、质量管理体系与措施、安全管理体系与措施、环境保护管理体系与措施、工程进度计划与措施、资源配备计划、技术负责人、其他主要成员、施工设备、试验和检测仪器设备等。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]