[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100618":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100618,779,1,"单选题","下列关于资格预审与资格后审的说法错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","公开招标通常采用资格预审方式",false,{"key":16,"text":17,"correct":14},"B","资格预审可以减小评标工作量",{"key":19,"text":20,"correct":14},"C","采用邀请招标，一般采用资格后审",{"key":22,"text":23,"correct":24},"D","对投标人的资格审查在评标后进行的称为资格后审",true,"2020版教材P50-51 资格后审是指开标后由评标委员会对投标人资格进行审查的方法。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]