[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100613":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100613,779,1,"单选题","根据《标准施工招标文件》，关于评标委员会对投标文件质疑的说法，错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","评标委员会以书面形式要求投标人书面澄清质疑问题",false,{"key":16,"text":17,"correct":18},"B","评标委员会约请投标人当面澄清并作会议记录",true,{"key":20,"text":21,"correct":14},"C","评标委员会不接受投标人主动提出的澄清说明",{"key":23,"text":24,"correct":14},"D","投标人的书面澄清说明作为投标书的组成文件","2020版教材P54-57 本题考查的是评标工作。选项B必须以书面形式要求投标人澄清，投标人也必须以书面形式作出澄清，不能有当面解释作出会议纪要的形式。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]