[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100595,779,1,"单选题","关于定标的说法，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定中标人的权力归评标委员会",false,{"key":16,"text":17,"correct":18},"B","招标人在评标委员会推荐的中标候选人中确定中标人",true,{"key":20,"text":21,"correct":14},"C","招标人可以根据自己的意愿确定中标人",{"key":23,"text":24,"correct":14},"D","中标通知书发出后，招标人有权拒绝订立合同","2020版教材P45 本题考查的是招标程序。招标人应该根据评标委员会提出的评标报告和推荐的中标候选人确定中标人，也可以授权评标委员会直接确定中标人。 如果招标人授权评标委员会确定中标人，评标委员会可将排序第一的投标人定为中标人，提交发包人请其与中标人签订施工合同。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]