[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100593":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100593,779,1,"单选题","与邀请招标相比，公开招标的特点是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","竞争程度低",false,{"key":16,"text":17,"correct":14},"B","评标量小",{"key":19,"text":20,"correct":14},"C","招标时间短",{"key":22,"text":23,"correct":24},"D","费用高",true,"2020版教材P39 本题考查的是招标方式。公开招标所需时间长、费用高；邀请招标节约招标费用和节省时间。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]