[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100589":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100589,779,1,"单选题","某施工项目招标采用经评审的最低投标价法评标，招标文件规定工期提前1 个月，评标优惠30 万元。某投标人报价1000 万元，工期提前1 个月，如果只考虑工期因素，则其评标价应为（）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1030",false,{"key":16,"text":17,"correct":14},"B","1000",{"key":19,"text":20,"correct":21},"C","970",true,{"key":23,"text":24,"correct":14},"D","950","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]