[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100583":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100583,779,1,"单选题","投标报价有算术错误，下列关于投标报价的修正，说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","如果大写金额与小写金额不一致的，以大写金额为准",true,{"key":16,"text":17,"correct":18},"B","如果总价金额与依据单价计算出的结果不一致的，以总价金额为准",false,{"key":20,"text":21,"correct":18},"C","评标委员会对投标报价进行修正后，即对投标人具有约束力",{"key":23,"text":24,"correct":18},"D","投标人不接受修正价格的，可以进一步补正","",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]