[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100574,779,1,"单选题","某施工项目招标，四家投标人的报价和评标价分别为：甲，1800万元、1870万元；乙，1850万元、1890万元；丙，1880万元、1820万元；丁，1990万元、1880万元，则中标候选人中排序第一的应为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","甲",false,{"key":16,"text":17,"correct":14},"B","乙",{"key":19,"text":20,"correct":21},"C","丙",true,{"key":23,"text":24,"correct":14},"D","丁","本题考查的是最低评标价法。按评标价从低到高的顺序选择中标候选人，不考虑报价的高低。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]