[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100559":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100559,779,1,"单选题","根据《标准施工招标文件》，关于评标委员会对投标文件质疑的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","评标委员会以书面形式要求投标人书面澄清质疑问题",false,{"key":16,"text":17,"correct":18},"B","评标委员会约请投标人当面澄清并作会议记录",true,{"key":20,"text":21,"correct":14},"C","评标委员会不接受投标人主动提出的澄清说明",{"key":23,"text":24,"correct":14},"D","投标人的书面澄清说明作为投标书的组成文件","2020版教材P52-54 在审查过程中，审查委员会可以用书面形式要求申请人对所提交的资格预审申请文件中不明确的内容进行必要的澄清或说明。申请人的澄清或说明应采用书面形式，并不得改变资格预审申请文件的实质性内容。申请人的澄清和说明内容属于资格预审申请文件的组成部分。招标人和审查委员会不接受申请人主动提出的澄清或民明。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]