[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100518":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100518,779,1,"单选题","按照建设项目总进度目标论证的工作步骤，项目结构分析后紧接着需要进行的工作是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","调查研究和收集资料",false,{"key":16,"text":17,"correct":14},"B","项目的工作编码",{"key":19,"text":20,"correct":14},"C","编制各层进度计划",{"key":22,"text":23,"correct":24},"D","进度计划系统的结构分析",true,"",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]