[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100517":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100517,779,1,"单选题","在工程项目实施阶段，项目监理机构及时为承包商办理工程预付款，属于项目监理机构在进度目标控制过 程中采取的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":21},"C","经济措施",true,{"key":23,"text":24,"correct":14},"D","合同措施","进度控制的措施应包括组织措施、技术措施、经济措施及合同措施。其中，经济措施包括： （1）及时办理工程预付款及工程进度款支付手续； （2）对应急赶工给予优厚的赶工费用； （3）对工期提前给予奖励； （4）对工程延误收取误期损失赔偿金。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]