[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100503":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100503,779,1,"单选题","某招标项目，招标人在原定投标截止之日前10d发出最后一份书面答疑文件，则此时投标截止 时间至少延长（ ）d。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",true,{"key":16,"text":17,"correct":18},"B","10",false,{"key":20,"text":21,"correct":18},"C","15",{"key":23,"text":24,"correct":18},"D","20","补充内容：招标文件的澄清与修改 1.招标文件的澄清 如果招标人发现招标文件中的错误，或要对招标文件中的部分内容进行修改，应在投标截止时间15天前，以书 面形式修改招标文件，并通知所有已购买招标文件的投标人。如果修改招标文件的时间距投标截止时间不足15天， 相应延长投标截止时间。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]