[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100470,779,1,"单选题","（2020年真题）根据《标准设备采购招标文件》中的通用合同条款，合同约定设备在出厂”前 买方参与交货前检验，卖方在设备已包装完毕准备启运前通知买方的，监理人的正确做法是（ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","同意卖方启运，改为设备安装前检验",false,{"key":16,"text":17,"correct":18},"B","停止启运，按合同约定进行交货前检验",true,{"key":20,"text":21,"correct":14},"C","停止启运，卖方自行检验后再包装启运",{"key":23,"text":24,"correct":14},"D","同意启运，视为卖方违约并扣合同价15%的违约金","P146 本题考查设备采购合同履行管理。专用合同条款约定买方参与交货前检验的，合同设备交货前，卖方应会同买方代表根据合同约定对合同设备进行交货前检验并出具交货前检验记录，有关费用由卖方承担。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]