[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100449":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1100449,779,1,"单选题","根据《标准设备采购合同》的规定，买方在收到卖方提交的买方签署的（ ）证书或已生效的结清款支付函正本一份，并经审核无误后（ ）内，向卖方支付结清款。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","缺陷责任期届满，14天",false,{"key":16,"text":17,"correct":14},"B","缺陷责任期届满，28天",{"key":19,"text":20,"correct":14},"C","质量保证期届满，14天",{"key":22,"text":23,"correct":24},"D","质量保证期届满，28天",true,"本题考查的是设备采购合同中合同价格与支付。买方在收到卖方提交的买方签署的质量保证期届满证书或已生效的结清款支付函正本一份，并经审核无误后28日内，向卖方支付合同价格的5%的结清款。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]