[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100419":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100419,779,1,"单选题","（2020年真题）根据《标准施工招标文件》，关于进度款支付证书的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进度款支付证书应由监理人审查承包人进度付款申请单后签发",false,{"key":16,"text":17,"correct":14},"B","监理人出其进度款支付证书视为监理人已批准承包人完成该部分工作",{"key":19,"text":20,"correct":21},"C","进度款支付证书应经发包人审查同意并签认后由监理人出具",true,{"key":23,"text":24,"correct":14},"D","进度款支付证书- - 经签发监理人无权修改","P104-107 监理人在收到承包人进度付款申请单以及相应的支持性证明文件后的14 天内完成核查.提出发包人到期应支付给承包人的金额以及相应的支持性材料。经发包人审查同意后，由监理人向承包人出具经发包人签认的进度付款证书。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]