[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100415":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100415,779,1,"单选题","（2020年真题）根据《标准施工招标文件》中的通用合同条款，发包人负责提供的材料和工程设备经验收后，接收保管和施工现场内二次搬运所发生的费用由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","发包人和承包人",{"key":23,"text":24,"correct":14},"D","发包人和材料设备供应商","P102-104 发包人提供的材料和工程设备验收后，由承包人负责接收、保管和施工现场内的二次搬运所发生的费用。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]