[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100414":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100414,779,1,"单选题","（2020年真题）根据《标准施工招标文件》中的通用合同条款，发包人根据实际情况向承包人提出提前竣工要求的，应在提前竣工协议中明确的内容是（ ） ．",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人修订的进度计划和赶工措施，发包人提供的条件和追加的合同价款",true,{"key":16,"text":17,"correct":18},"B","发包人提出的赶工要求和追加合同价款，承包人要求的奖励办法",false,{"key":20,"text":21,"correct":18},"C","发包人修订的进度计划和奖励办法，承包人提出的赶I措施和追加的费用",{"key":23,"text":24,"correct":18},"D","承包人修订的进度计划和施工条件要求，发包人的工期要求和追加的合同价款","P99-102 如果发包人根据实际情况向承包人提出提前竣工要求，由于涉及合同约定的变更，应与承包人通过协商达成提前竣工协议作为合同文件的组成部分。协议的内容应包括:承包人修订进度计划及为保证工程质量和安全采取的赶工措施;发包人应提供的条件;所需追加的合同价款;提前竣工给发包人带来效益应给承包人的奖励等。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]