[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100412":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100412,779,1,"单选题","（2020年真题）根据《标准施工招标文件》中的通用合同条款，在暂停施工期间，负贵施工现场保护和安全保障的主体是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":14},"B","监理人",{"key":19,"text":20,"correct":21},"C","承包人",true,{"key":23,"text":24,"correct":14},"D","监理人和承包人","P99-102 不论由于何种原因引起的暂停施工，监理人应与发包人和承包人协商，采取有效措施积极消除暂停施工的影响。暂停施工期间由承包人负责妥善保护工程并提供安全保障。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]