[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100411":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100411,779,1,"单选题","（2020年真题）通用条款规定的费用是指（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工合同履行中发生的不计利润的合理开支",true,{"key":16,"text":17,"correct":18},"B","施工合同履行中由发包人支付给承包人的全部款项",false,{"key":20,"text":21,"correct":18},"C","发包人对承包人履行合同支付的结算价",{"key":23,"text":24,"correct":18},"D","承包人完成工程的实际成本","P104-107 通用条款内对费用的定义为，履行合同所发生的或将要发生的不计利润的所有合理开支，包恬管理费和应分摊的其他费用",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]