[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100404":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100404,779,1,"单选题","(2016年真题)工程施工过程中，对于变更工作的单价在已标价工程量清单中无适用或类似子目时，应由监理人按照（ ）的原则商定或确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本加酬金",false,{"key":16,"text":17,"correct":18},"B","成本加利润",true,{"key":20,"text":21,"correct":14},"C","成本加规费",{"key":23,"text":24,"correct":14},"D","直接成本加间接成本","本题考查的是变更管理。已标价工程量清单中无适用或类似子目的单价，可按照成本加利润的原则，由监理人商定或确定变更工作的单价。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]