[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100403":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100403,779,1,"单选题","(2015年真题)根据《标准施工合同》，缺陷责任期满承包人提交最终结清单前，仍有权提出索赔要求。索赔的原因应是在（ ）发生的事项。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工期间",false,{"key":16,"text":17,"correct":14},"B","竣工验收期间",{"key":19,"text":20,"correct":21},"C","缺陷责任期内",true,{"key":23,"text":24,"correct":14},"D","合同有效期内","监理人收到承包人提交的最终结清申请单后的14天内，提出发包人应支付给承包人的价款送发包人审核并抄送承包人。 发包人应在收到后14天内审核完毕，由监理人向承包人出具经发包人签认的最终结清证书。 发包人应在监理人出具最终结清证书后的14天内，将应支付款支付给承包人。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]