[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100393":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100393,779,1,"单选题","(2017年真题)根据《标准设计施工总承包招标文件》中的《合同条款及格式》，在合同履行过程中，承包人提出合理化建议时，正确的处理程序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人向监理人提出——监理人与发包人协商——监理人向承包人发出变更指示",true,{"key":16,"text":17,"correct":18},"B","承包人向监理人提出——监理人向发包人报告——发包人与承包人协商合同变更",false,{"key":20,"text":21,"correct":18},"C","承包人向发包人提出——发包人与监理人协商——监理人向承包人发出变更指示",{"key":23,"text":24,"correct":18},"D","承包人向发包人提出——发包人通知监理人——监理人向承包人发出变更指示","承包人对发包人提出的合理化建议，均应以书面形式提交监理人。监理人与发包人协商是否采纳承包人提出的建议。建议被采纳并构成变更的，监理人向承包人发出变更指示。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]