[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100392":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1100392,779,1,"单选题","(2016年真题)根据《标准施工合同》，发包人在施工合同订立阶段的义务是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织施工单位测设施工控制网",false,{"key":16,"text":17,"correct":14},"B","组织监理单位编制施工组织设计",{"key":19,"text":20,"correct":21},"C","组织设计单位进行设计交底",true,{"key":23,"text":24,"correct":14},"D","组织勘察单位进行现场查勘","本题考查的是发包人义务。在施工合同订立阶段，发包人的义务包括：（1）提供施工场地；（2）组织设计交底；（3）约定开工时间。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]