[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100388":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100388,779,1,"单选题","(2015年真题)施工合同履行期间市场价格浮动对施工成本造成影响时，是否允许调整合同价格要视（ ）来决定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同工期长短",true,{"key":16,"text":17,"correct":18},"B","材料价格浮动幅度",false,{"key":20,"text":21,"correct":18},"C","合同计价方式",{"key":23,"text":24,"correct":18},"D","劳动力价格浮动幅度","本题考查的是订立合同时需要明确的内容。合同履行期间市场价格浮动对施工成本造成的影响是否允许调整合同价格，要视合同工期的长短决定。工期在12个月以内的简明施工合同的通用条款没有调价条款；工期12个月以上的施工合同，由于承包人在投标阶段不可能合理预测一年以后的市场价格变化，因此应设有调价条款。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]