[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100380":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1100380,779,1,"单选题","(2019年真题)根据《标准施工招标文件》的施工合同文本通用合同条款，“合同进度计划”是指由（ ）的施工进度计划。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人审定",false,{"key":16,"text":17,"correct":18},"B","监理人批准",true,{"key":20,"text":21,"correct":14},"C","承包人投标文件提交、",{"key":23,"text":24,"correct":14},"D","招标文件提出","2.审查进度计划 监理人对承包人的施工组织设计中的进度计划审查，监理人审查后，应在专用条款约定的期限内，批复或提出修改意见，否则该进度计划视为已得到批准。经监理人批准的施工进度计划称为“合同进度计划”。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]