[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1100375":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1100375,779,1,"单选题","(2018年真题)根据《标准施工合同》，下列引起暂停施工的情形中，属于承包人的责任的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工技术事故",true,{"key":16,"text":17,"correct":18},"B","异常恶劣天气",false,{"key":20,"text":21,"correct":18},"C","不可抗力",{"key":23,"text":24,"correct":18},"D","因设计缺陷导致的设计变更","（四）暂停施工 承包人责任引起的暂停施工，增加的费用和工期由承包人承担； 发包人暂停施工的责任，承包人有权要求发包人延长工期和（或）增加费用，并支付合理利润。",{"id":6,"name":27,"category":28,"favorite":29},"合同管理","建筑工程",0]